Prior to issuing any permits in a WQRA a Construction Management Plan must be submitted to the City as follows:

A. Construction Management Plans are subject to Type I review per ZDC Chapter 510 and the City of Wood Village Construction Standards.

B. Construction Management Plans shall provide the following information:

(1) Determination of a WQRA and description of work to be done in compliance with the requirements listed in Table 2.

(2) Scaled site plan showing a demarcation of a WQR and/or an HCA and the location of excavation areas for building foundations, utilities, stormwater facilities, etc.

(3) Location of site access and egress that construction equipment will use.

(4) Equipment, material staging and stockpile areas.

(5) Erosion and sediment control measures.

(6) Measures to protect trees and other vegetation located within the potentially affected WQR and/or HCA. A root protection zone shall be established around each tree in the WQR or HCA that is adjacent to any approved work area. The root protection zone shall extend from the trunk to the outer edge of the tree’s canopy, or as close to the outer edge of the canopy as is practicable for the approved project. The perimeter of the root protection zone shall be flagged, fenced, or otherwise marked and shall remain undisturbed. Material storage and construction access is prohibited within the perimeter. The root protection zone shall be maintained until construction is complete.

When required for a property that does not include a designated natural resource, the Construction Management Plan shall show the protective measures that will be established on the applicant’s property.